Issue 2ten dates across 6 projects

Ten dates across six projects, starting Oct 22

Permit-first project leads for Gulf Coast suppliers, fabricators and equipment reps.

Project hubs: Texas · Louisiana · FERC · LDEQ

1: Moore County, FERC CP26-581. 2: Carthage, FERC CP26-547. 3: Brownsville, FERC CP26-532. 4: Baton Rouge, FERC CP26-582. 5: Quintana Island, FERC CP03-75. 6: Westlake, LDEQ LA0127532Gulf of Mexico1Moore County2Carthage3Brownsville4Baton Rouge5Quintana Island6Westlake
Where the six projects are. Numbers match the items below.

Ten dates across six projects a fab shop can sell into, ordered by scope, then paperwork renewals in Also filed.

The permit clock

  1. 1NGPL Amarillo ExpansionFERC · Docket CP26-581-000

    • Notice of application (Passed)
    • Interventions, protests and comments due (Passed)
  2. 2Gulf South Texas GatewayFERC · Docket CP26-547-000

    • Final EIS (coming up)
    • Federal decision deadline (coming up)
  3. 3Rio Grande LNG Train 6FERC · Docket CP26-532-000

    • Final EIS (coming up)
    • Federal decision deadline (coming up)
  4. 4FGT Brooks Lake RelocationFERC · Docket CP26-582-000

    • Prior notice filed (Passed)
    • FR notice (Passed)
    • Protests and interventions due (coming up)
  5. 5Freeport LNG regas removalFERC · Docket CP03-75-000

    • EA issued (Passed)
    • Texas Historical Commission concurrence filed (Passed)
    • Federal authorization deadline (coming up)
  6. 6LIP JV WestlakeLDEQ · Permit LA0127532

    • Draft notice published (Passed)
    • Public hearing (coming up)
    • Comments due (coming up)

Dates come from agency and company records. Today is marked for Oct 23, 2026. Nearer deadlines sit in October and November; longer federal EIS clocks run into 2027.

  1. FERC · Docket CP26-581-000 · Project page

    1. NGPL Amarillo Expansion

    NGPL: Amarillo Expansion, new Compressor Station 112 (Moore and Deaf Smith Counties, TX)

    Stage
    Abbreviated certificate application filed Sept 17, 2026. FERC issued its notice of application dated Oct 1 (published in the Federal Register Oct 6) and set the intervention deadline. The project is a new Compressor Station 112 in Moore County with four 5,500 hp gas-fired units (22,000 hp) and auxiliary facilities, plus a new delivery point in Deaf Smith County. It adds 321,200 Dth/d, aimed at power generation.
    Owner
    Natural Gas Pipeline Company of America LLC.
    Designing or building
    What you could sell
    Compressor packages and skids, station and yard piping, gas coolers, pipe supports, and metering for the Deaf Smith delivery point.
    Date to watch
    Oct 22, 2026, 5:00 pm ET. Motions to intervene, protests and comments are due at FERC. (Passed)
    This week
    Pull the application from eLibrary (docket CP26-581) to see the station layout, then ask NGPL's project group how the station packages will be bought.
  2. FERC · Docket CP26-547-000 · Project page

    2. Gulf South Texas Gateway

    Gulf South: Texas Gateway Pipeline (seven East Texas counties and Beauregard Parish, LA)

    Stage
    EIS scoping is under way. On Sept 28, Gulf South filed minor workspace and alignment updates. The application covers 155 miles of 36-inch and 42-inch greenfield pipe from the Carthage Compressor Station to new Gillis delivery points. It also covers two Titan 130 units at Carthage, a Titan 250 and a Titan 130 at the Magasco station, and a new 13,410 hp Cleveland Compressor Station in San Jacinto County. Rounding it out are three meter stations, seven mainline valves and six pig launcher and receiver sites, adding 1.8 million Dth/d. FERC's August notice rounds the length to about 154 miles. Counties: Panola, Shelby, San Augustine, Sabine, Jasper, Newton and San Jacinto, TX, plus Beauregard Parish, LA.
    Owner
    Gulf South Pipeline Company, LLC.
    Designing or building
    What you could sell
    Meter station skids, pig launchers and receivers, valve settings, compressor station piping and pipe supports.
    Date to watch
    The draft EIS is planned for April 2027 and opens a 45-day comment period. The final EIS is set for Sept 24, 2027, and the federal decision deadline is Dec 23, 2027.
    This week
    Ask Gulf South's project team when meter station and launcher and receiver fabrication will be bid.
  3. FERC · Docket CP26-532-000 · Update from issue 1 · Project page

    3. Rio Grande LNG Train 6

    NextDecade: Rio Grande LNG Train 6, Brownsville (Cameron County, TX)

    Stage
    EIS review. On Sept 28, 2026, Rio Grande LNG filed a limited response to scoping comments. FERC's notice describes one new liquefaction train of about 6.03 million tonnes a year, a new marine jetty (Berth 3), and about 303 acres disturbed for the train and 22 for the berth. Update from issue 1.
    Owner
    Rio Grande LNG Train 6, LLC (NextDecade).
    Designing or building
    What you could sell
    Pipe, structural steel, module work, marine and berth steel, piling.
    Date to watch
    The draft EIS is planned for January 2027 and opens a 45-day comment period. The final EIS is set for June 25, 2027, and the federal decision deadline is Sept 23, 2027.
    This week
    Ask Rio Grande LNG's project contacts which Train 6 packages are being priced now.
  1. FERC · Docket CP26-582-000 · Project page

    4. FGT Brooks Lake Relocation

    Florida Gas Transmission: Brooks Lake Relocation (East Baton Rouge Parish, LA)

    Stage
    Prior notice request filed Sept 18, 2026 under FGT's blanket certificate. The Federal Register notice ran Oct 1. FGT would relocate its mainline to avoid the Brooks Lake Diversion Canal Project, building three generally parallel replacement segments totaling about 1.58 miles of 24-inch and 30-inch pipe.
    Owner
    Florida Gas Transmission Company, LLC.
    Designing or building
    What you could sell
    24-inch and 30-inch line pipe, fabricated bends and tie-in assemblies, valves and coating.
    Date to watch
    Nov 27, 2026, 5:00 pm ET. Protests, motions to intervene and comments are due at FERC.
    This week
    Ask FGT's project team when the relocation goes to bid and who is handling the tie-ins.
  2. FERC · Docket CP03-75-000 · Update from issue 1 · Project page

    5. Freeport LNG regas removal

    Freeport LNG: removal of old regas facilities, Quintana Island (Brazoria County, TX)

    Stage
    FERC staff issued the environmental assessment Sept 18. On Sept 29, Freeport LNG filed the Texas Historical Commission's concurrence. The project removes the regasification facilities, underground piping, equipment foundations and paving, and modifies or relocates what liquefaction still needs. Update from issue 1.
    Owner
    Freeport LNG Development, L.P.
    Designing or building
    What you could sell
    Demolition, scrap purchase, civil work, tie-in piping and small mechanical work at a running LNG terminal.
    Date to watch
    Dec 17, 2026. That's the 90-day deadline for other federal agencies' authorization decisions.
    This week
    Ask Freeport LNG's contracts group how and when the removal work will be bid.
  3. LDEQ · Permit LA0127532 · Project page

    6. LIP JV Westlake

    Louisiana Integrated Polyethylene JV: new water discharge permit, Westlake (Calcasieu Parish, LA)

    Stage
    LDEQ published a new draft water discharge permit on Oct 1, 2026 and scheduled a public hearing. EPA's record for permit LA0127532 puts the facility at 2201 Old Spanish Trail, Westlake. The draft package is the place to confirm new production equipment.
    Owner
    Louisiana Integrated Polyethylene Joint Venture LLC.
    Designing or building
    What you could sell
    If the permit is for new production at the site, process water and wastewater piping, tanks and treatment skids. The draft package will show how much is new.
    Date to watch
    Nov 5, 2026, 6:00 pm public hearing at Westlake City Hall. Written comments are due Nov 9, 2026, 4:30 pm CST.
    This week
    Read the draft permit package to see what's being added, then decide whether it's worth a call before the hearing.

Also filed

Part 70 renewals and a discharge permit for a running plant. No new equipment named in the notice.

  • 0040-00225-V5Kinder Morgan Louisiana Pipeline, Eunice Compressor Station No. 760 (Acadia Parish, LA). Part 70 renewal and modification (V4 to V5). Comments due Nov 4, 2026, 4:30 pm CST. LDEQ public notice · Project page
  • 1360-00008-V8Tennessee Gas Pipeline, Compressor Station 823, Kinder (Jefferson Davis Parish, LA). Part 70 renewal and modification (V7 to V8). Comments due Nov 4, 2026, 4:30 pm CST. LDEQ public notice · Project page
  • Part 70 airET Gathering and Processing, Springhill Compressor Station (Webster Parish, LA). Part 70 renewal and modification. Comments due Nov 5, 2026, 4:30 pm CST. LDEQ public notice · Project page
  • LA0120529Shintech Plaquemine plant water discharge permit (Iberville Parish, LA). Comments due Nov 3, 2026, 4:30 pm CST. LDEQ public notice · Project page

TDLR · TABS registrations filed Sept 30 to Oct 2, 2026

Big builds registered in Texas

These aren't deadlines. A TDLR registration is an accessibility filing. It doesn't authorize construction, and the owner-listed start is the owner's own estimate, which can move. All four starts are still ahead. They're listed in start order. Dollar amounts are on the TDLR pages; we don't reprint them here.

  1. DAL130 data center, Circle T Ranch campus, Westlake (Tarrant County, TX)

    Owner
    Circle T Owner LP
    TDLR project
    TABS2027002672, with TABS2027002674 and TABS2027002675 on the same campus
    Listed size
    224,152 sq ft data center, plus a 5,000 sq ft auxiliary water building and a 1,500 sq ft access control building
    Owner-listed start (not a deadline)
    Dec 1, 2026 (owner-listed completion Jun 1, 2027)
    Design firm on the filing
    Ci Design
  2. Project Hyper, Spur Building 2, near Jayton (Kent County, TX)

    Owner
    Spur DC Owner 2 LLC
    TDLR project
    TABS2027002499
    Listed size
    759,262 sq ft, new construction
    Owner-listed start (not a deadline)
    Jan 13, 2027 (owner-listed completion May 25, 2029)
    Design firm on the filing
    HKS, Inc.
  3. Skybox Hutto 4, core and shell, Hutto (Williamson County, TX)

    Owner
    Hutto Data Center Campus, LLC
    TDLR project
    TABS2027002367
    Listed size
    846,300 sq ft, new construction
    Owner-listed start (not a deadline)
    Jan 20, 2027 (owner-listed completion Oct 30, 2028)
    Design firm on the filing
    Corgan Associates Inc.
  4. Project Hyper, Spur Building 1, near Jayton (Kent County, TX)

    Owner
    Spur DC Owner 1 LLC
    TDLR project
    TABS2027002494
    Listed size
    759,262 sq ft, new construction
    Owner-listed start (not a deadline)
    Jan 31, 2027 (owner-listed completion Jun 7, 2029)
    Design firm on the filing
    HKS, Inc.

What these filings are. A TDLR registration is an accessibility filing. It doesn't authorize construction, and its dates can change. A Part 70 renewal can be paperwork, so read the modification before you spend time on it. A draft permit isn't a final permit, and a pending application can be changed or withdrawn. FERC schedule dates are staff targets and can move. The "What you could sell" line is our judgment, not a bid list.

See you next Friday.
The ScopePlex team

Know someone who bids this work? Forward them this issue.