Interstate natural gas pipelines, compressor stations and LNG terminals in Texas and Louisiana leave a paper trail at the Federal Energy Regulatory Commission. Two docket types matter most to business development teams: the pre-filing docket, which carries the PF prefix, and the certificate docket, which carries the CP prefix. They mark different stages of a project, and they call for different moves from the people who want to build or supply it.
This guide explains what each docket is, what our records show for Texas and Louisiana projects, how to read a docket on FERC eLibrary, and what EPC firms, contractors and suppliers can do with each filing while the design is still open.
What is the difference between a FERC PF docket and a CP docket?
A PF docket is the voluntary pre-filing review an applicant opens before it submits a formal application, and FERC's rules require it for LNG terminals. A CP docket is the certificate application itself under the Natural Gas Act. The PF docket comes first, often 6 to 12 months before the CP filing, and marks a project still taking shape.
In pre-filing, the sponsor works with FERC staff and other agencies before anything is formally proposed. Routes, sites and facility layouts are still being drawn. Draft environmental resource reports, scoping notices, open house announcements and agency comment letters land on the PF docket. The sponsor is public, the project name is public and the general location is public, but the scope can still move.
The CP docket opens when the sponsor files the formal certificate application. At that point the project description is far more settled: the facilities, the route, the compression, the terminal components and the proposed schedule are on paper. FERC staff run the environmental review on this docket, the applicant answers data requests here, and the certificate order is issued here. After an order, the same docket keeps working. Implementation plans, variance requests and requests to begin construction are filed under the CP number.
CP dockets also live a long time. A sponsor can amend an existing certificate, add facilities or ask for more time, and those filings often come in under the original docket with a new subdocket suffix. That is why an LNG project can show a fresh 2026 filing on a docket that was opened years earlier.
| Docket | Stage | What it tells you | What to do |
|---|---|---|---|
| PF (pre-filing) | Before a formal application | Sponsor, project name, rough site or route, consultants working the file | Identify the owner's engineering and environmental team, start the relationship, learn the likely scope |
| CP (certificate application) | Formal application under the Natural Gas Act | Defined facilities, route, schedule and environmental review | Get on bid lists, prepare supplier qualification, track data responses that change scope |
| CP after the certificate order | Implementation | Construction plans, variances and requests to proceed | Confirm award status, watch for construction release, follow up with the selected contractor |
What the record shows: FERC PF and CP docket numbers on LNG and pipeline projects
Across Texas and Louisiana, the database holds 26 projects carrying a FERC certificate (CP) docket and 2 projects carrying a pre-filing (PF) docket. No project record carries both today. Those projects sit alongside 3,210 FERC filings from our LNG and pipeline feeds, so most of the FERC activity you will see lands on certificate dockets.
| Measure (Texas and Louisiana) | Count |
|---|---|
| Projects with a FERC certificate (CP) docket | 26 |
| Projects with a FERC pre-filing (PF) docket | 2 |
| Projects with both on one record | 0 |
| FERC filings from the LNG and pipeline feeds | 3,210 |
The low PF count is not a sign that pre-filing is rare. Pre-filing is a window, not a permanent state. Once the formal application is filed, the work moves to a new CP docket, and the PF docket goes quiet. A database snapshot on any given day will show more projects in the certificate stage than in pre-filing simply because the certificate stage lasts longer and keeps generating filings after the order.
The zero in the table matters for anyone tracking a project from its first appearance. Today no single project record in the database shows both a PF number and a CP number. If you are following a pre-filing project, check eLibrary for the later CP docket yourself when the sponsor files its application, and treat the two dockets as one project in your own pipeline.
For context, FERC dockets are a narrow slice of the 7,350 public projects in the database, of which 3,097 are in Texas and 690 are in Louisiana. They are a small slice with a large payload: a single certificate docket can carry a pipeline, several compressor stations, meter stations and a marine terminal, each with its own scope for civil, mechanical, electrical and instrumentation work.
Where to find it and how to read it
Search FERC eLibrary by docket number. The letters give the docket type, PF for pre-filing and CP for a certificate case. The digits that follow roughly mark the year the docket opened, then a sequence number, then a subdocket suffix. Open the docket, sort by date, read the newest filings first, then return to the original application for scope.
A docket number such as CP15-490-005 reads in three parts. CP is the type. 15-490 identifies the original docket. The final suffix separates related proceedings under that docket, such as an amendment or a request for an extension. A suffix other than 000 usually means the project is back before FERC for a change, and changes are often where new scope appears.
In a PF docket, read these filings first:
- The initial request to use the pre-filing process. It names the sponsor, describes the proposed facilities in general terms and often lists the consultants working on the environmental and engineering files.
- Draft resource reports. These show the route or site options, the land requirements and the facility list as the sponsor sees it at that moment.
- Scoping notices and open house announcements. They confirm the project is active and give a sense of where it will be built.
- Agency and landowner comments. They flag route changes, crossings and constraints that drive construction method and cost.
In a CP docket, read these filings first:
- The application. The project description, facility list, maps and proposed schedule are the core of any scope assessment.
- Responses to FERC data requests. These revise the design and often add or remove facilities.
- The environmental document and the certificate order. The order sets the conditions the builder must meet.
- Implementation plans and requests to begin construction. These are the filings that tell you the field work is close.
On our project pages, the FERC docket number sits on the project record with the filings listed by date, so you can see the last time the sponsor or FERC touched the case without opening eLibrary. The sources page lists the FERC LNG and pipeline feeds the database reads.
Recent examples from our project pages
Recent FERC activity on our Texas and Louisiana records includes two new pre-filing dockets for LNG projects and a run of certificate filings in November 2026. Port Arthur LNG North opened PF26-14-000 with a filing on Nov 5, 2026, and the Texas LNG Expansion Project followed with PF26-17-000 on Nov 6, 2026. Both are Texas projects at the pre-filing stage.
| Project | State | Docket | Type | Filing date |
|---|---|---|---|---|
| Port Arthur LNG North | TX | PF26-14-000 | Pre-filing | Nov 5, 2026 |
| Texas LNG Expansion Project | TX | PF26-17-000 | Pre-filing | Nov 6, 2026 |
| Delfin LNG | LA | CP15-490-005 | Certificate | Nov 10, 2026 |
| Amarillo Project | TX | CP26-581-000 | Certificate | Nov 12, 2026 |
| Harrison County Power Project | TX | CP26-565-000 | Certificate | Nov 13, 2026 |
| CP2 LNG Expansion Project | LA | CP26-533-000 | Certificate | Nov 17, 2026 |
| Kosciusko Compressor Station Replacement Project | TX | CP26-24-000 | Certificate | Oct 7, 2026 |
| Corpus Christi Stage 4 LNG Project | TX | CP18-513-000 | Certificate | Sep 23, 2026 |
The two PF dockets are the earliest public markers for those LNG projects. A business development team that starts now has the whole pre-filing window to learn who is doing the front end engineering, which environmental consultants are on the file and what the owner expects to build, before a formal application fixes the scope.
The certificate dockets show the range of work that runs through FERC. CP2 LNG Expansion Project in Louisiana and Delfin LNG are LNG cases. Delfin's filing came in under a subdocket suffix on a docket opened years earlier, which is the pattern to watch for amendments and extensions. Corpus Christi Stage 4 LNG Project shows the same thing: a 2026 filing on a docket that began with an 18 in its number.
Not every certificate case is a terminal. The Amarillo Project and the Harrison County Power Project are new 2026 certificate dockets in Texas, and the Kosciusko Compressor Station Replacement Project is a reminder that compressor replacements carry mechanical, electrical, controls and civil scope of their own. Smaller certificate cases like these are often where regional contractors and suppliers have the best odds.
What to do with it
Each docket stage supports a different action. A PF docket is the time to learn the owner and the design team. A new CP docket is the time to qualify for bid lists and supply. A late CP filing is the time to confirm who won the work and sell to them.
- EPC firms: use PF dockets to identify the sponsor's engineering contacts and the likely contracting strategy. Read the CP application for facility counts and schedule before committing proposal resources.
- Pipeline and mechanical contractors: watch CP dockets for route maps, crossing methods and compressor facilities. Data responses that change the route can change spread counts and access.
- Electrical and instrumentation contractors: compressor station and terminal filings describe power supply, controls and buildings. Replacement projects are steady work that rarely gets press coverage.
- Suppliers: the facility list in a CP application is a bill of materials in outline. Use it to time outreach to the owner and to the EPC once the order is near.
Docket numbers do the tracking for you. Save the PF or CP number for each project you care about, set eLibrary to notify you of new filings, and check our project record for the latest filing date. If you want the week's new FERC, state permit and interconnection activity in one place, the free weekly email covers it. For the full set of linked project records, filters and filing histories, see the database plans.
For plain answers to other permit questions, the answers page collects them in one place.
Every project in this guide sits in the database with its filings. See what a member gets