How to Read TDLR TABS Registrations for $50 Million Plus Projects

What a Texas TDLR TABS registration lists, why big data center and plant builds show up there first, and how to read one to find owners and timing.

Every Texas building project that costs $50,000 or more has to be registered with the Texas Department of Licensing and Regulation for accessibility review under the Texas Architectural Barriers program, known as TABS. The threshold is low, so the registry holds strip centers and clinics alongside data center halls and manufacturing plants. For a business development team, the value is in the large builds hiding inside that volume.

A registration names the owner, the location, the estimated cost and the planned start and completion dates. That is the core of a qualified lead. This guide explains how to read one, what the database shows about registrations on large industrial and data center projects, and what to do with each filing.

What is a TDLR TABS registration and why does it reveal big projects?

A TDLR TABS registration is the accessibility review filing Texas requires for building projects that cost $50,000 or more. It lists the owner, location, estimated cost, and planned start and completion dates. Data center halls and plants file one like any other building, so the registration puts a named owner, a cost and a schedule on the public record.

Most permits that business development teams watch cover the process side of a project: air, water, the grid connection. TABS covers the buildings. A data center campus is mostly buildings, and so is a large share of a manufacturing plant, so TABS is often the filing that turns a rumored project into one with an address, a cost estimate and a date.

Three features make TABS useful for large projects:

  • One registration per building. A campus with several halls files several registrations. Our records show this directly: 205 registrations spread across 126 projects. Building numbers in the project name (Building 5, Building 8, Building B, Buildings 1 to 3) tell you which phase a filing covers.
  • Dates on the record. The planned start and completion dates give you a working schedule even when the owner has said nothing publicly.
  • The owner as registered. Registrations are often filed under a project entity rather than the operator's brand. Several of our page addresses carry entity names such as DA12 LLC, Childress DC3 LLC or AIL Investment LP, while the project is known by a different name. Search for both.

TABS has limits. The estimated cost on a registration is the building cost the registrant entered, not the full project cost, and it may leave out process equipment, site work or utility scope. The dates are plans, not commitments. Treat a registration as strong evidence that a building is designed and headed for construction, then confirm the rest from other filings.

What the record shows: TDLR TABS registrations on large industrial and data center builds, with owner and project name

The database links 205 TDLR TABS registrations to 126 Texas projects. 85 projects had a registration in 2026 and 50 in 2025, some in both. Data centers make up 91 of the projects and manufacturing 21. We do not split registrations by dollar value, so apply a $50 million filter yourself using the cost on each filing.

The database tracks TABS registrations that belong to large industrial and data center builds. It does not ingest every small retail or office registration in the state. That choice is what keeps the list useful: the 126 projects are the ones a contractor or supplier in the industrial and data center markets would actually pursue.

SectorProjects with a TABS registration
Data Centers91
Manufacturing21
Food and Life Sciences4
Power2
Water and Environmental2
Chemicals1
LNG and Terminals1
Refining and Fuels1
Unassigned3

Data centers dominate for a simple reason. Their scope is building scope, so TABS catches them. TABS is also the most common way a Texas data center first appears in the database: of 136 data center projects in Texas, 91 first appear through a TDLR TABS registration, ahead of the TCEQ central registry at 32 and SEC filings at 8. A project can appear through more than one source.

CountyProjects with a TABS registration
Ellis15
Dallas13
Tarrant9
Harris7
Collin7
Bexar6
Denton5
Bosque4

The county list reads like a map of the Dallas and Fort Worth data center market, with Ellis County at the top. Harris and Bexar show that the registrations are not only a north Texas story, and the Panhandle examples below show campuses landing far from the metro areas.

Where to find it and how to read it

Search the TDLR TABS site by project number, which is TABS followed by digits, such as TABS2027005620. You can also search by owner, city or county. Open the registration and read the owner, the project name, the location, the estimated cost and the start and completion dates. Those fields tell you who to call, where and when.

Read each field with a business development question in mind:

  • Owner. This is who registered the building. If it is a project entity, find the parent through the project name, the address or other filings. The owner is your first call, not the architect.
  • Project name. Building numbers and phase names tell you whether this is the first hall on a campus or a later one. A later building on a known campus means the owner's team and contracting model are already in place.
  • Location. The street address and county let you match the registration to air permits, utility filings and county agendas for the same site.
  • Estimated cost. Use this field to apply your own size cut, such as $50 million. Remember it may cover the building shell and fit out only.
  • Start and completion dates. These set your outreach window. Trades and suppliers who sell after the start date are usually selling to a contractor already on site.
  • Design firm and contacts. Where listed, these tell you who is drawing the building and who to approach about specifications.

After the registration, TDLR's process continues with plan review and, after construction, an inspection. New activity on a registration is a sign the project is moving through those steps.

On our project pages, the TABS number and registration date sit on the project record next to the other filings for the same site, so you can see in one view whether a building registration lines up with an air permit, a grid request or a county agenda item. The sources page lists every feed the database reads.

Recent examples from our project pages

Recent TABS registrations on our project pages are mostly data center buildings in north Texas and the Panhandle. Equinix DA13 in Dallas registered TABS2027005620 on Nov 11, 2026. Clocktower Quanah Building 5 in Hardeman County registered on Oct 27, 2026, and Compass Datacenters registered Building 8 of its Red Oak campus in Ellis County on Oct 15, 2026.

ProjectCountyTABS numberRegistered
[Equinix DA13 data center](/projects/da12-llc-data-center-dallas)DallasTABS2027005620Nov 11, 2026
[Clocktower Quanah data center, Building 5](/projects/19000-200-holdings-llc-data-center-hardeman)HardemanTABS2027004544Oct 27, 2026
[Compass Datacenters DFW III Campus (Red Oak), Building 8](/projects/compass-datacenters-data-center-ellis)EllisTABS2027003683Oct 15, 2026
[Circle T Data Center, DAL130 Building, Westlake](/projects/dal130-data-center)TarrantTABS2027002672Oct 2, 2026
[Colovore Alliance (Colovore DFW02)](/projects/ail-investment-lp-data-center-denton)DentonTABS2027001701Sep 22, 2026
[Project Hyper Childress, Buildings 1 to 3](/projects/childress-dc3-llc-data-center-childress)ChildressTABS2027000824Sep 11, 2026

Several patterns show up in these filings. The Compass Datacenters Red Oak campus is on Building 8, which tells you the owner has a repeat design and an established contracting setup on that site. A firm that is not already on that campus needs to reach the owner's construction team before the next building, not after it registers.

The Clocktower Quanah campus in Hardeman County and Project Hyper Childress in Childress County are rural Panhandle sites. Remote campuses need temporary facilities, crew housing, long haul logistics and local subcontractors, and the registration dates tell those suppliers when to show up.

Equinix DA13 and Colovore DFW02 show the entity issue. Their page addresses carry DA12 LLC and AIL Investment LP, the names on the record, while the projects are known by the operator name. The STACK Infrastructure DFW02 Campus, Building B in Lancaster, Dallas County, and the Circle T DAL130 building in Westlake round out a cluster of north Texas data center buildings that registered within weeks of each other.

What to do with it

Use a TABS registration as the trigger to qualify and contact. Check the estimated cost against your size cut, find the parent owner behind the registering entity, match the address to other filings for the same site, and reach the owner or general contractor before the start date on the registration.

  • General contractors and EPC firms: a later building on a known campus is a repeat buyer. Track building numbers and approach owners between phases.
  • Electrical and mechanical contractors: data center registrations mean large power distribution, cooling and controls scope. Match the address to grid and air filings to size it.
  • Suppliers: the start date is the latest useful date for specification work. Reach the design team and the owner's procurement group well before it.
  • Service and staffing firms: rural campuses in counties such as Hardeman and Childress need local support that metro contractors do not bring.

The free weekly email lists new building registrations alongside air permits and grid requests each week. To filter all 126 projects by county, sector and date, and to see every linked filing on each record, see the database plans. Other permit questions are answered on the answers page.

Watch the county counts as well. Ellis at 15 and Dallas at 13 are where repeat buildings are most likely to keep registering, which makes them the places where a standing relationship with owners pays off fastest.

Every project in this guide sits in the database with its filings. See what a member gets