Market data · MISO queue and EIA

Louisiana solar projects

This page counts the Louisiana solar projects requested in the grid queue and the requested MW they list. It shows how many there are, how large they are, when they expect to come online and which counties they sit in. Project names, owners, sizes per project, schedules and filings are in the database.

42
projects requested in the grid queue
8,220 MW
8,220 requested MW in total
196 MW
average requested size
2 of 42
owners traced to a parent company (5%)
42 of 42
have an expected online date in the queue

Louisiana solar projects in the MISO interconnection queue and EIA's planned power plant list with an update since Jan 1, 2025, cancelled and withdrawn entries excluded. As of Oct 25, 2026.

Expected online year

Most projects expect to come online in 2026 or 2027

YearBar = projectsCountReq. MW
2024 (past due)192
2025 (past due)3600
2026153,000
2027152,948
20284800
20291140
20303640

Louisiana solar projects in the MISO interconnection queue and EIA's planned power plant list with an update since Jan 1, 2025, cancelled and withdrawn entries excluded. As of Oct 25, 2026. Year is the expected online date shown in the filing. Amber marks the year with the most projects. A past year means the project is late against its own stated date.

Size bands

Most projects request 150 to 300 MW

BandBar = projectsCountShare
Under 50 MW37%
50 to 150 MW921%
150 to 300 MW2457%
300 MW and up614%

Louisiana solar projects in the MISO interconnection queue and EIA's planned power plant list with an update since Jan 1, 2025, cancelled and withdrawn entries excluded. As of Oct 25, 2026. Covers the 42 projects with a stated size. Right column is the share of those.

Top counties

The 12 counties with the most solar projects

CountyBar = projectsCountRequested MW
Jefferson Davis Parish5890
Morehouse Parish5962
Ouachita Parish41,180
Beauregard Parish3640
Rapides Parish3830
Sabine Parish3492
Acadia Parish2270
Franklin Parish2110
Washington Parish2350
Avoyelles Parish1200
Bolivar Parish180
Desoto Parish1240

10 more in other parishes.

Louisiana solar projects in the MISO interconnection queue and EIA's planned power plant list with an update since Jan 1, 2025, cancelled and withdrawn entries excluded. As of Oct 25, 2026. County pages are planned.

Project names, owners and filings: in the databaseGet the free weekly

Entered the queue, by quarter

New entries per quarter, 2025 to 2026

QuarterBar = projectsCountReq. MW
2025 Q11240
2025 Q20
2025 Q30
2025 Q41300
2026 Q12427
2026 Q21200
2026 Q30
2026 Q40

Louisiana solar projects in the MISO interconnection queue and EIA's planned power plant list with an update since Jan 1, 2025, cancelled and withdrawn entries excluded. As of Oct 25, 2026. Counts only projects still in the queue, so older quarters lose cancelled projects. 37 of the 42 were first filed before 2025 or carry no filing date, so they are not in this table.