Texas solar + storage projects

This page counts the Texas solar + storage projects requested in the grid queue and the requested MW they list. It shows how many there are, how large they are, when they expect to come online and which counties they sit in. Project names, owners, sizes per project, schedules and filings are in the database.

49
projects requested in the grid queue
16.0 GW
16,023 requested MW in total
341 MW
average size of the 47 with a stated size
11 of 49
owners traced to a parent company (22%)
48 of 49
have an expected online date in the queue

Texas solar + storage projects in the ERCOT interconnection queue and EIA's planned power plant list with an update since Jan 1, 2025, cancelled and withdrawn entries excluded. As of Oct 25, 2026.

Expected online year

Most projects expect to come online in 2027 or 2028

YearBar = projectsCountReq. MW
2025 (past due)1150
202661,254
2027218,236
2028165,619
20294765

Texas solar + storage projects in the ERCOT interconnection queue and EIA's planned power plant list with an update since Jan 1, 2025, cancelled and withdrawn entries excluded. As of Oct 25, 2026. Year is the expected online date shown in the filing. Amber marks the year with the most projects. A past year means the project is late against its own stated date.

Size bands

Most projects request 300 MW and up

BandBar = projectsCountShare
Under 50 MW00%
50 to 150 MW36%
150 to 300 MW2145%
300 MW and up2349%

Texas solar + storage projects in the ERCOT interconnection queue and EIA's planned power plant list with an update since Jan 1, 2025, cancelled and withdrawn entries excluded. As of Oct 25, 2026. Covers the 47 projects with a stated size. Right column is the share of those.

Top counties

The 12 counties with the most solar + storage projects

CountyBar = projectsCountRequested MW
Jones County3685
Kaufman County3651
Lamar County31,332
Cameron County2481
Franklin County2615
Matagorda County2606
Wilson County21,600
Wise County2453
Angelina County1126
Archer County1600
Austin County1600
Bee County1151

25 more in other counties. 1 with no county stated.

Texas solar + storage projects in the ERCOT interconnection queue and EIA's planned power plant list with an update since Jan 1, 2025, cancelled and withdrawn entries excluded. As of Oct 25, 2026. County pages are planned.

Project names, owners and filings: in the databaseGet the free weekly

Entered the queue, by quarter

New entries per quarter, 2025 to 2026

QuarterBar = projectsCountReq. MW
2025 Q12548
2025 Q20
2025 Q30
2025 Q42151
2026 Q10
2026 Q22500
2026 Q30
2026 Q40

Texas solar + storage projects in the ERCOT interconnection queue and EIA's planned power plant list with an update since Jan 1, 2025, cancelled and withdrawn entries excluded. As of Oct 25, 2026. Counts only projects still in the queue, so older quarters lose cancelled projects. 43 of the 49 were first filed before 2025 or carry no filing date, so they are not in this table.